Alconbury Brook Flood Group – end September 2024
This is a quick update of work done in the last two weeks since our last bulletin.
Maintenance momentum.
20+ volunteers have done brilliant work over the last couple of week-ends clearing those hard to maintain sections of the brook bank that the idb can’t reach with the tractor flail mower.
We have also sprayed reeds over a 300m section of the brook near the A1 flyover.
Our next volunteer events will be on October 12th and 19th at Alconbury Weston and 700m downstream of the A1 flyover. If you would like to take part please contact Debbie at debbiehose@talk21.com . Reed spraying will continue for several weeks.
Nuns Bridge A generous farmer who farms adjacent to Nuns Bridge has agreed to take the spoil from the clearance. A spoil disposal exemption has been registered. We are also grateful for further offers of funding.
Hamerton Pond Project. A basic design has now been agreed with landowner. An outline of the proposal is with Cambridgeshire Archaeology. Issues with access to the site are being investigated.
Flood Alleviation Scheme Reports on the potential impact of 4 of the options have been completed by the modelling consultants JBA. Reports on the upstream storage and downstream conveyance options are still awaited. The downstream conveyance report is due during the first week in October
Tanglewoood Pond: Details are now with the diocesan owners of the site to get permission for the work to be undertaken. Thanks to the EA who are in the process of applying for a grant for the work on our behalf.
Soil Projects. Using Chicory as a test plant since it was plentiful on the Allotment Herbal Ley experiment we were interested to find that some treatments did produce differences.
The addition of mycorrhizal fungi increased plant weight, and root depth, volume and mass.
The addition of Phosphite and PGA (thank you Unium Bioscience) also had the same effect, and increased the number of branches plants had.
Although these are very preliminary findings, they are useful pointers for future experiments.
Farm Walk: If you would like to attend our farm walk between 6pm and 7.30pm on October 9th when we will be talking about methods of measuring plant activity and yield, contact
Alconbury Brook Flood Group Some of what’s happened during July 2024
Alderman’s Pond/Alconbury Weston Pond: The last week has seen finishing touches including further removal of spoil and the restoration of the banks prior to sowing with deep rooted wild flowers, and native hedging. We have added a connection to another ditch so that the pond now collects rainwater run-off from over 100ha. Additional inlet and outlet culverts have been added. The inlet dam is also complete. Final touches such as a lifebuoy, safety signage, and an interpretation board to help users of the nearby footpath to understand how the pond works both for flood mitigation and wildlife habitat.
We were very pleased to host a visit by members of the Regional Flood and Coast Committee. The main function of the committee is to advise the Environment Agency on the use of funds to prevent flooding and coastal erosion. From our point of view, the visit was an opportunity to demonstrate how we as a group are serious and can competently provide excellent value and benefit. In addition the scale of flood management interventions in an impermeable catchment generating 4 million cubic metres (December 2020) of run-off in a few hours need to be BIG!
We have applied to the Huntingdonshire Futures grant scheme for restorative planting which will provide an environmental benefit, a volunteering opportunity and contribute to the flood mitigation provided by the site. (Fingers crossed).
Vinegar Hill east. It seems unlikely, given the advice we have received, that there will be archaeological or planning complications for this project since we plan to restore the ridge and furrow structures and restore the pond to it’s original dimensions. We now have concept drawings ready to present to the landowner and hope that given their permission work will be able to take place in the spring.
Vinegar Hill rainwater capture gardens: We are pleased to say that Chelsey and Jared from our construction partners Silver Fern have completed their Streetworks training which means that we can now apply for the necessary permit for work to occur. The permitting is time consuming so it seems likely that work will be delayed until late autumn at the earliest.
New experiments: Cowpasture Farm have drilled another special deep rooted seed mix for us. This time ‘winter wild bird’ mix which is found in corners of many of the catchment farms. The objectives are much the same: to find if we can increase soil porosity and yield at the same time along with other measures.
Our Herbal Ley experiment at Cowpasture Farm has now been cut. We are in the process of analysing stacks of data. One thing that stands out is that where the soil is compacted, yields are smaller both above and below ground. The same small scale version of the experiment at Alconbury Allotments is demonstrating porosity differences between treatments.
We are also looking at the widespread problem of leatherjackets which are the root eating larvae (not helpful if you want deep rooted plants). We will be trying a type of bacteria which attacks the larvae as a means of control. Our DNA works shows the bacteria are already there but only in small quantities.
Following our collaboration on sediment, Rothampsted Research (RR) have applied for £1.9 million to continue the work. In this catchment there is evidence that top-soil is being washed away. The RR bid if successful will include opportunities for some farmers in our cluster to have demonstration sediment capture approaches constructed on their land.
The microplastics trap funded by Mott Macdonald is now installed thanks to hard work by volunteers. Apart from checking that it’s still there, it will be several months before the trap contents in analysed.
Thank you to everyone who visited our stall at the village fete and the wonderful volunteers who spent the afternoon talking non-stop, answering questions, and signing up new volunteers. (We look forward to working with you soon).
Our new rain gauges are working well. As can be seen here the beginning of July was pretty wet. If the same amount of rain had fallen on saturated soil we would have seen a very full brook.
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Alconbury Brook Flood Group Some of what’s happened during June 2024
Downstream funding: We are delighted to report that the EA is providing £10,000 worth of funding for clearance of the brook from the area around the Holiday Inn and Racecourse. This part of the brook has been neglected for a while with a build up of trees and debris in the brook. The work will be done by the Internal Drainage Board in the late autumn.
Downstream Group: The Flood Group has got together with other partners affected by flooding further downstream including Huntingdon Racecourse and The Holiday Inn Hotel, both of which have been badly affected by flooding. We are pleased with the news of the £10,000 input. The group has now met formally to look at a number of issues beyond the A141 flyover, as far as Garkies Sluice, where the brook runs into the River Ouse. Hopefully there will be more news as we make progress.
Our first Farm Walk. Over 20 people, including farmers and those with an interest in projects going on at Cowpasture Farm, attended our first event. It started with a talk about our experiments at the farm and how they might help farmers improve yields and reduce flooding. We looked in particular at how soil condition can enhance or reduce plant growth and yields and affect water holding capacity. After that the group tried some of the citizen science methods the group has used to measure how compact the soil is and it’s impact on root growth. Finally, we walked to a flood group pond restoration. On the way Stacy Branson pointed out ways in in which biodiversity on the farm is being enhanced. We learnt a lot about running a farm walk, but generally felt quite pleased with our first attempt. The next one will be later in the summer. You will get an invitation. Our thanks to Anglian Water, Natural England and Unium Bioscience for funding and support and especially Cowpasture Farm.
New Alconbury Weston Project. We are working with the EA and County Council on a project on the east side of Vinegar Hill. Fairly steep hills provide rapid run-off when the soil is saturated.
The most straightforward parts of the project is are the restoration of the Tanglewood Pond to its original size and the sensitive restoration of the ancient ridge and furrow in the surrounding field, which could act as a sequence of swales to hold up flood water for possibly 24-36 hours.
We are pleased to say that the project has attracted funding from 2 possible sources. Work on more detailed concepts and design are is underway.
School Lane microplastics monitoring. The school Lane ditch has an interesting journey from Alconbury Weald, under the motorway, through agricultural land and then along beside a residential street. Will the special nets find a lot of microplastics? Where will it have come from?
Sediment Project. We are very grateful to Dr Simon Pulley from Rothamsted Research who has written his report about the origins of sediment in the brook having been assisted by our citizen scientists. He says that in many places in the country most sediment comes from riverbanks rather than run-off from farmland. In this catchment, however, farmland is a more important likely source of sediment in some of the brook’s tributaries. Loss of sediment material is a loss of topsoil for farmers and also causes a brook flow problem. We will now be looking at some parts of the brook to see if we can understand more about the sediment issues.
Flood Group AGM: We were delighted that nearly 70 people turned up (more than last year and on a Friday night!). It was a very positive event. If you were able to come it was great to see you and we hope to see you again at the next AGM.
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Alconbury Brook Flood Group Some of what’s happened during May 2024
Alconbury Weston Storage and Wildlife Pond:
Flood Alleviation Scheme. We have received an update from the EA team working on option feasibility. (Our additions in italics.)
JBA (the modelling company evaluating costs and benefits) are continuing to progress the options modelling and will be providing outputs from other options in the coming months.(they have worked through and reported on one option, evaluation of future options should now be quicker).
Soil Science Our first DNA results for a field at Cowpasture Farm are in.
The purpose of this work is to find out if groups of soil microbes assist soil rain infiltration and carbon storage.
The analysis is ongoing but fascinating since it reveals past and present plant DNA.
It looks like an ancient type of wheat was grown on the field and possibly grape vines.
Soil Mentor ap. 5 farms are using the ap which enables recording and analysis of soil health data.
The farms are currently adding the fields they want to monitor to the ap. (many thanks to them).
Farm Walk No 1
Out first farm walk (funded by Natural England) is scheduled for June 12th. The soil experiments and hands on opportunities to do soil measurements will be included plus a visit to a restored pond (thanks to the Wildlife Trust for Beds, Cambs and Northants).
All recipients of this bulletin are welcome and the invitation is attached. Places are limited so please respond quickly. There will be 2 other walks later in the summer. Thanks for this too to T H Branson.
Telemetry 14 soil moisture sensors are prepared of which 8 are deployed either on Cowpasture Farm or Alconbury Allotments. They are already generating data about soil rain capacity.
Downstream Group The group has a draft report following a walk from the Holiday Inn Brampton to Garkies Sluice (where Alconbury Brook joins the Ouse) Various issues arose from this review. The group will be meeting at the racecourse later in June.
Flood Group AGM 2024. Please attend our AGM at 7.00p.m. on May 31st at the Memorial Hall. We will provide and update on our work over the last year. There will be a chance to ask questions and make suggestions. Look forward to seeing you there!!
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Donate if you can to www.justgiving.com/thealconburybrookfloodgroup
Alconbury Brook Flood Group Some of what’s happened during April 2024
Alconbury Weston Pond: We are delighted that at last work is well underway on the large biodiversity and flood storage pond behind Sallows Farm. Top-soil has been removed and work has started on removing the layers of clay below.
Deeper Roots Project: Our experiments are intended to see if deeper rooted plants enable the soil to hold more water.
Alconbury Flyover: National Highways have sourced funding for the area under the flyover on the left hand side opposite the brook. Their design team are in the process of putting together a plan. The area in the meantime has been cordoned off with barriers to help stop too many vehicles parking there as this has compacted the surface so water does not drain away.
Downstream Collaboration: A group consisting of the Brampton Holiday Inn, The Racecourse, the Flood Group and others affected by flooding downstream of the villages is meeting for the first time on April 30th , a meeting which will include walking from the Holiday Inn to the River Ouse to look at how flow along that stretch of the brook could be improved. We continue to value the support that the Racecourse and the Hotel give to our other projects.
EA flood alleviation Scheme (FAS): Data from the consultants who are doing the option modelling has started to be sent back to the EA team working on a FAS for the Alconbury’s. There should be a little more news by the AGM (see below). One of many good reasons to attend.
Flood Group AGM 2024. Please attend our AGM at 7.00p.m. on May 31st at the Memorial Hall. We will provide and update on our work over the last year. There will be a chance to ask questions and make suggestions. Look forward to seeing you there!!
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Donate if you can to www.justgiving.com/thealconburybrookfloodgroup
Alconbury Brook Flood Group
Some of what’s happened during March 2024
Hydroplanters at Sports and Social Club and Memorial Hall
Hydroplanters - Vinegar Hill: Vinegar Hill suffers from significant surface water run-off which threatens homes at the bottom of the hill
Alconbury Weston Pond: We have applied to have the archaeology condition removed now that the archaeologists have reported. The removal of the condition has to be considered by statutory consultees which takes 3 weeks (from March 11th). We hope that the Planning department will provide a swift decision after that so that work on the pond can start. Everything is in place for this to happen.
Natural England Partnership.: Part of our agreement includes working with 5 farmers on using a soil health phone ap called ‘SoilMentor’. We are delighted that 5 farms will be taking part. Healthy soil and reduced flood risk go hand-in hand.
Also as part of the partnership we are providing open farm events (Farm Walks) to explain some of the experiments and innovations we and the Cowpasture Farm are trying. If you would like to be included in the Farm Walk invitation mailing list please email info@alconburybrookfloodgroup.co.uk.
EA Flood alleviation scheme: Option modelling will take until the summer
Heritage Bridge, Alconbury: We are pleased to report that the berm which had built up in front of the bridge has been removed by the Internal Drainage Board on behalf of the Environment Agency. Many thanks to them.
Telemetry: Internet of things sensors communicate over short distances with ‘gateways’ which can then transmit information over large distances. We have successfully tested another new gateway which covers sensors in the Gidding area. Our internet of things company c-Things is preparing numerous soil moisture, flow and rain sensors for deployment in the next few weeks. We have started to show volunteers how to log in to the data being collected so they can use it to help them predict flooding, and for others as a farming tool. We plan to demonstrate our telemetry system more at our AGM in May.
Reed Spraying Course: Many thanks to Alconbury Parish Council for their significant contribution towards the cost of one our members doing a pesticide use course
Sediment tracking project: Sediment build up is a major problem preventing easy flow in the brook. Volunteers have been collecting more soil samples and we have successfully retrieved the traps from each of the main Brook tributaries. The samples and trap contents are being analysed by Rothamsted Research to understand the movement of sediment in the catchment. The brook carries many thousands of tonnes of good agricultural soil away from farms. Some of it clogs up the brook and reduces flow.
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Donate if you can to www.justgiving.com/thealconburybrookfloodgroup
Alconbury Brook Flood Group
Many of our projects not mentioned, but here’s a flavour of what we’ve done during February 2024
Hydro-planters (large drained soakaways which also filter water) now installed at two strategic locations in the villages:
Alconbury Weston and other ponds
Partnership Agreement with Natural England
Work has started on these projects including using some of the funding to purchase a phone app for farmers called ‘Soil Mentor’ This helps farmers to improve productivity and soil health. Healthy soil helps rain infiltration.
Farmers and community members will be invited to ‘farm walks’ starting at the end of April to have a tour of some of the innovative work we are doing on Cowpasture Farm. (Many thanks to T H Branson and Son)
Environment Agency Flood Alleviation Scheme
Other projects
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Donate if you can to www.justgiving.com/thealconburybrookfloodgroup
Alconbury Brook Flood Group Bulletin January 28th 2024
Hydrogardens
Alconbury Weston and other Ponds
A Partnership Agreement with Natural England is finalised. It will help to fund work with farms on soil health and deeper roots that will contribute to flood prevention
The Brook Bank that had subsided on the Alconbury Village Green near Brookside has been partly filled by us (with EA permit exemption). It will be surfaced to the normal height with top-soil and appropriately re-seeded.
The removal of silt from upstream of the Heritage Bridge in Alconbury will occur during week commencing on Feb 20th weather and brook permitting.
All of the sediment traps are working including a replacement for the one which disappeared at the beginning of the month. We now have quite a number of soil samples. If you fancy a walk near Gidding or Winwick, let us know and we will give you some sample bags.
A number of additional sensors and a new LORAWAN gateway have been ordered and will be installed shortly. These were funded by the Cambridgeshire Community Foundation and Anglian Water. Daily use of the data has allowed us to determine the relationship between depth and flow. The peak flow during the flood in early January was about 16m3/s, almost exactly one Olympic swimming pool flows past every minute.
We have perfected a technique using AI to count useful soil fungi. These encourage the right sort of root growth.
The heavy rain at the beginning of January saw no indoor flooding in the Alconbury’s or Hamerton but it was exceptionally close. 1cm in the case of the lowest home.
EA Flood Alleviation scheme: No further news.
Contact us to volunteer at info@alconburybrookfloodgroup.uk
Donate if you can to www.justgiving.com/thealconburybrookfloodgroup
Alconbury Brook Flood Group Report September 2023
EA Flood alleviation scheme: We have been invited to look at the model outputs this week in a meeting with the EA and the modelling company JBA. These outputs will be in the form of maps and other similar data showing the extent of flooding predicted for different return periods e.g. 1 every 20 years; 50 years and so on. We will be able to compare the model with real life. The first step will be to ensure the model is valid.
IF the new model then shows that more properties flood more often than the old model, then maybe we will be able to show more benefit to be gained from a possible flood alleviation scheme. Extra benefit will mean extra funding for any scheme. Testing the model against possible schemes will take until January 2024.
GreenBlue: Acting on the information received from GreenBlue during an on-site meeting, plans to install the HydroPlanters at the Memorial Hall are developing well. A local contractor has quoted for the project. Surplus spoil will be disposed of thanks to excellent advice from Mr Philip Baker. GreenBlue have offered further support as we begin and during the work. Funding is imminent . When the time comes, we will be looking for some willing volunteers to help with some aspects of preparation and installation We are aiming for the work to be done before the end of November.
Volunteer work and Brook Maintenance.
Internal Drainage Board will be flailing banks in the next 2 weeks
Volunteers have been tackling the places inaccessible to a tractor and have done excellent work beyond the flyover, near the ford and near the Heritage Bridge.
In October we will be doing work near the Alconbury Weston Ford, downstream of the Alconbury Sewerage Works, and a soil measuring morning.
Alconbury Weston Pond Archaeology: Quotes for the archaeology and necessary excavation have been acquired and funding has been assured. The next step is to get a brief for the work from Cambridgeshire County Council. Our chosen archaeological organisation will then produce a work schedule which will need to be approved. Hopefully by the next edition of our bulletin we will be able to report that the archaeology can begin. Although we have been assured that it is unlikely that Iron Age people built a village on a boggy field, there is always the risk that we turn up a Roman temple which might slow things down considerably!! We still hope that actual excavation of the pond will take place well before Christmas.
Harts Pond: We have met with Phil Hart the farmer who, with minor modifications, has approved the plan. A few pieces of paperwork to sign and then hopefully volunteers will move in, in October to complete some tree work, and then the contractor to do the excavation.
Small meander adaption- Permit application approved work to be done later in the autumn.
Charity: We have applied for a ‘Just Giving’ page
Nitrate measurement: Volunteers have carried out a second survey at the beginning of September. Again levels are higher as you move downstream, slightly lower than August’s measurements.
Debris in the brook at Hinchingbrooke Country Park is still there despite our request that it be removed. Nuns Bridge is badly blocked topped off with a supermarket trolley. The debris may block the bridge and the trolley may get stuck in Garkies Sluice.
This is very disappointing since we were promised action last month and the month before! Watch this space.
Herbal Ley Project: Seed sowing for at least 2 of the experiments during October. Volunteers will be doing soil testing during October. Exciting! Work has started on our first video, link to YouTube channel in next bulletin.
Sensor Project: We will know if Cambridgeshire Community Foundation can support the purchase of additional sensors and the community dissemination of the information by November 1st
Mill Road Drains. A change in staff at CCC has resulted in a slight delay in inspection for further action. Our County Councillor has assured us this will be discussed this week and following a Flood Group request the 3 gullies in Mill Road/Brookside bend area were jetted and suctioned. It seems there is likely to be a blockage in the pipes running underground to the brook. We have requested a joint onsite visit with the Highways as the first step in resolving this issue. This has been reported to CCC for follow-up and our County Councillor for support.
Brampton Cross Meeting with BX team held and a number of questions submitted. The Parish Council are arranging a public meeting with BX in October. We hope to have answers to our questions before the meeting.
Flood Conference: 5 members of the Flood Group attended Cambridgeshire’s second Flood Conference with us all returning with useful info and contacts. Back in January 23 Cambridgeshire made a short video about TABFG, we have seen a preview and understand it will soon be released. Link to video in next bulletin.
Alconbury Brook Flood Group Report August 2023
EA flood alleviation scheme. Good news that the long-awaited model has been released by the modelling company. Once its checked, the options and combination of options will be tested. We hope to have more information about the model in the next edition including how closely it matches the lived experience of our communities. The option modelling will last until January.
Green-Blue Rainwater Garden Project: A visit from a member of the GreenBlue team was very beneficial. We have a better understanding of what needs to be done, how it will be done and who will do the work. We also, now understand the process to set this project in motion. It is likely that work will not be able to start until early Autumn but planning is in hand. (photo of meeting )
Alconbury Weston Pond: Planning permission has been granted but conditional on a full scale archaeological survey. This will be an expensive addition and will cause delays. Planning permission has taken 10 months and the archaeology condition was added at the last moment. To say we are disappointed would be an understatement however resilience is a necessary attribute for flood groups! If you know a reasonably priced chartered archaeologist, let us know!!
Harts Pond: Outline and costing approved by the Hunts and Beds Wildlife Trust. Next steps are farmer and landowner consent. We hope this work will take place mid-October. We will need help from volunteers to clear on 2 sides of the pond before work can commence.
Meander adaption- EA officer (thanks to him) appointed to help us with the application is now satisfied that our pre-submission is satisfactory and meets the necessary requirements. Work on this is likely in November and will have to be done entirely by hand. Debbie will be asking for volunteers.
Charity Registration: The Flood Group Charity is now registered which gives us the advantage of being a legal entity. Our Charity number is 1204246.
Nitrate measurement: Volunteers have been collecting water samples from the brook to measure various chemicals. This will allow us to track water flow and sediment from upstream. Currently, nitrate levels are nearly three times higher at Alconbury Ford compared to Hamerton and Gidding.
Debris in the brook at Hinchingbrooke Country Park is still there despite our request that it be removed. A campaign of letter writing will commence shortly.
Herbal Ley Project: Excellent progress, first areas will be seeded with deep rooted plants in September at Cowpastures Farm in Gidding and on an allotment in Alconbury. Progress will be recorded on a YouTube channel. Testing of the plots has already been going on for some time, but there will be an opportunity for volunteers to do some soil measurements in the autumn. Soil moisture and rainfall will be measured automatically using our sensor system.
Sensor Project: The FG has applied for funding from the Cambridgeshire Community Foundation to support the purchase of additional sensors and the dissemination of the information collected to the Community. The real time data will help people make accurate predictions about flood risk and times.
Mill Road Drains Following a FG request to Cambs County Council the 3 gullies in Mill Road/Brookside bend area were jetted and suctioned. It was noted at the time that there was likely to be a blockage in the pipes running underground to the brook. This has been reported to CCC and our County Councillor for follow up and further action.
Brampton Cross is a new possible new development to the south of Alconbury. The FG are keen to understand the scale and detail of the scheme to that we can evaluate flood risks and the measures which will be required to mitigate them. We have a meeting later this week with the developers to discuss the information that will help us.
Fallen Willow: Thanks to FG members who removed a Willow Tree which had fallen across the brook downstream of Alconbury Weston ford. This would have been a problem if we had experienced heavy rain.
Contact us at: info@alconburyfloodgroup.uk
Alconbury Brook Flood Group Report July 2023
Anglian Water Partnership.
We are delighted to report that Anglian Water have approved our bid for £100,000. This will go towards the Alconbury Weston Pond, The GreenBlue Urban project, and the Soil Science project.
Flood Alleviation Scheme (FAS)
Work on the Alconbury Brook model is still underway
Pond Projects
Sensor Project
GreenBlue Urban project
Herbal Ley Project
National Highways Partnership
Hinchingbrooke Country Park and Racecourse
Village Fete:
Dozens of people stopped to chat. Very pleasant afternoon despite a bit of rain.
Call for sites
One of the ways in which Local Councils source and allocate land for potential future development is via a consultation exercise known as a “Call For Sites”. This allows developers to have building land assessed for inclusion as part of future local planning strategy. This process has now ended and the public can see the sites at: sites-submitted-in-call-for-sites.xlsx (live.com). If you want to see more detail and comment you need to put the site number into this website: Call for Sites Spring 2023 - What people say - Keystone (huntingdonshire.gov.uk). From a purely Flood Group point changes in the law later this year will require developers to do much more to reduce the impact of flooding and environmental harm. Will that be enough? Take a look and comment.
Alconbury Brook Flood Group Report June 2023
Flood Alleviation Scheme FAS
Pond Projects
Sensor Project
GreenBlue Urban project
Herbal Ley Project
Meeting with Olive Morley (CEO Huntingdonshire District Council)
Alconbury Brook Flood Group Report May 2023
FAS
Pond Projects
Flood Mobile
Gabions
Sensor Project
GreenBlue Urban project
Herbal Ley Project
Key Dates:
Our web-site: Home (alconburybrookfloodgroup.uk)
Contact us at: info@alconburyfloodgroup.uk
Alconbury Brook Flood Group Report April 2023
FAS
Pond Projects
Flood Mobile
Gabions
Sensor Project
Blue Green Urban project
Herbal Ley Project
Ashden Award
We are delighted to have been shortlisted for an award for innovative Community Nature Adaptation tackling flooding and climate change. This is an international award with shortlisted schemes from the UK, and many other countries. A final assessment will take place during June when assessors will visit us to review our work.
Alconbury Brook Flood Group Report March 2023
FAS
Pond Projects
Flood Mobile
Gabions
Sensor Project
Herbal Ley Project
Blue Green Urban (Modular surface water retention system which incorporates natural processes)
Ashden Award (£10,000) for communities working with water- next step if we are successful will be an assessor visit in the summer.
Alconbury Brook Flood Group Report February 2023
Overall picture is that progress is rather slow with FG waiting for news and progress in a number of areas.
FAS
Pond Projects
Video and Flood Mobile
Gabions
Sensor Project
Sensors and nodes working.
Herbal Ley Project
National Flood Forum- supporting flood groups
Alconbury Brook Flood Group Report January 2023
FAS
Pond Projects
Video
Gabions
Sensor Project
Herbal Ley Project
National Flood Forum
Racecourse
Alconbury Brook Flood Group Report 16th December 2022
Alconbury Flood Alleviation Scheme:
Ponds Project: Planning permission for Alconbury Weston Pond submitted awaiting response from District Council. Quote for work confirms that this will be an expensive project with flood group fund raising a priority in the new year. Buckworth pond planning application ready and being checked. Landowner has generously offered to submit on our behalf since this increases chance of the application being successful
Volunteer work: A further 8 dead trees removed from near Polecat Lane
Newsletter: December edition of the community newsletter delivered to all households. Many thanks to all who helped.
Data Project: Cambridgeshire CC, and cThings working with us to get on-line flow, soil moisture and rainfall measurements available on-line via 4G. Locations chosen and equipment due for testing after Christmas. Also a bid for £7500 to enTrade for soil moisture sensors for a partnership experiment with Natural England.
Charity Registration application. Submitted.
Alconbury Brook Flood Group (FG) Report November 26th 2022
Alconbury Brook Flood Alleviation Scheme.
Barford Reservoir
Many thanks to IDB Phil Lovesey and landowner Gary Davison
40 Ponds/NFM Two more NFM projects now completed this month. (left Black Lodge Pond by FG and FWAG and right Winwick new brook meanders, ponds and leaky dams by EA and FWAG) Black Lodge filling and emptying nicely in last few days. Winwick project significant project on 250m of brook upstream) FG
Thanks Lucy Jenkins FWAG and Karen Paterson EA)
Next two ponds are in planning process. AW-Philip Baker’s pond planning application submitted, Buckworth Brook scrape application with planning consultant.
Survey Community interaction with survey team revealed that they have been commissioned to do 100m intervals. We have suggested to EA that this may miss key bottlenecks and pinch points, and that these are important when improving the current models. Suggestions have been made to some additional cross sections that could be surveyed.
Sensor projects FG believes that accurate information about rainfall, soil moisture and flow is crucial to understanding the brook and measuring outcomes of interventions. FG has met with cthings and CCC to look at how we could integrate our sensors with their 3G data communication system. Very positive response. Visit planned to cthings HQ to develop technical side. Bid in to ‘entrade’ for £7500 towards sensors and nodes. FG is monitoring soil moisture and flow on a regular basis.
Alconbury Brook Flood Group (FG) Report October 23rd 2022
Alconbury Brook Flood Alleviation Scheme.
A meeting took place last week with EA about the Flood Alleviation Scheme (‘the options’). These are regular scheduled meetings.
Progress is being made.
EA and FG consensus that national contractors may not be able to price scheme so that cost/benefit ratio of 1 or more is reached.
Good discussion about possible ways forward that may show increased benefit and reduced cost in a different funding framework.
EA have commissioned a Survey Team to ‘map’ the brook. The resulting data will be the basis for flood models. Work will start their work November/December. This new step will cause some delay, but we anticipate will demonstrate greater potential benefit. In the meantime the ‘lived accounts’ of flooding will be used.
We are keen that the EA raise the potential storage capacity of the option upstream of AW when calculating the benefit of that option.
We also want the ‘benefit’ to include the work the FG are doing which has no cost to the Flood alleviation scheme.
40 Ponds project (Landscape Recovery/NFM)
CIL funding
Our CIL funding application was turned down. However again thanks to Ian Gardener, the District Council have agreed to look at ways to achieve the same objective. We have a meeting with the EA, Ian and the chief planning officer next week.
Flyover Gabions
Progress still being made with design work
Volunteers/ Maintenance
Fantastic work by volunteers this month, quality cutting by the IDB drivers
Under permit exemption silt has been removed from the old footbridge in Alconbury Weston and near the fly-over in Alconbury
The internal Drainage Board team have flailed the banks from Alconbury Weston to the lower part of Brooklands Farm (further than previous years). We are very pleased with the work done which has been careful and thorough.
The Flood Group Volunteers have continued to clear brush and bushes from the banks where the tractor mower has been unable to reach including near the start of Brooklands Farm, near the Alconbury Ford footbridge, banks of rear gardens on the High Street Alconbury and Alconbury Weston and several other sections of the brook.
Alconbury Brook Flood Group (FG) Report September 2022
Alconbury Brook Flood Alleviation Scheme.
FG submitted cross section data thanks to several members who helped with measurements. New brook survey had been commissioned by EA to improve modelling, will cause delay of 2-3 months
2nd meeting with EA on scheme options, main issue cost estimate too high and benefits too low
Discussion took place about how to improve the viability of the scheme including
JP also to look at rejected options for acceptable elements which might add to benefit
FG will look at acceptable concepts to see if they can be applied elsewhere in the catchment and make enquiries.
40 Ponds project (Landscape Recovery/NFM)
CIL funding
An application was submitted by the FG on behalf of Alconbury PC to install 10 trapped drains near the Village Green in Alconbury. The cost is very high, partly because so many services traverse the drain pipes. We have our fingers crossed.
Flyover Gabions
Progress being made with design work
Volunteers/ Maintenance
Team in Alconbury and Alconbury Weston have been working every Saturday and have cleared 700m of bank, and some silt/reeds under permit. Work will continue during October to:
We expect the Internal Drainage Board (who are doing the banks this year) to start and complete flail mowing of banks in the next few days so we can identify areas that still need work.
Cambridgeshire Flood Conference.
Cambridgeshire held a very helpful conference attended by several FG members. Very interesting talks including Flood-RE about insurance and help to ‘build back better’, and the National Flood Forum. We also presented our work. Many good contacts made, and conversations had. Good event.
Alconbury Brook Flood Group Report August 28th 2022
Alconbury Brook Flood Alleviation Scheme.
As a result of consultation, the main option now being evaluated is the upstream culverted bund at Alconbury Weston plus other complimentary options. The FAS website is being regularly updated so the public can check progress.
First of our regular meetings with EA discussed progress with acquiring funding which is going well with further funds from national infrastructure funding which is available to communities which have flooded twice or more in the last 10 years (e.g. 2016 and 2020).
EA reported that preliminary costings of some options being prepared.
Also helpful discussion about modelling. Flood Group looking at the cross section of the brook in a number of places to see if it has changed. This work has started and feedback provided to the EA about the section from the flyover to Armstrong’s Gorse.
FG reported on progress with upstream pond projects, successes and challenges (see below)
FG outlined conversations they had had with downstream businesses and how we could work together.
40 Ponds project (Landscape Recovery/NFM)
Positive meeting with FWAG and landowner regarding Black Lodge pond refurbishment. All looks good for this to happen in the next few months. FWAG and FG to meet contractor on site early September.
Hamerton pond project has fallen through, as a result FG are in the process of preparing a permitted development application for another site in Alconbury Weston. All being well the £10,000 being provided by CCC will go towards this as well as other funding.
The FG completed and submitted an application to the Wooley Wind Farm Fund for a grant to make a 1500m3 scrape next to Buckworth Brook. If the grant application is successful then autumn or spring completion anticipated.
CIL funding
CIL is the levy developers pay which is then given to communities to improve infrastructure.
Alconbury PC on behalf of the FG has applied for CIL funds to provide trapped drains on Brookside and at the end of the High Street. Trapped drains have an underground container to remove silt.
The current drains allow road silt to go straight into the brook which encourages reed growth. The reedy section of the brook in Alconbury is 50cm shallower because of the build up of silt.
Volunteer projects
We have a schedule for Saturdays in September to complement the maintenance work being done by the EA, also in September. We are starting with work around the Dutch Arches in Alconbury Weston, and just before and after the flyover in Alconbury. If you can volunteer contact Debbie Hose for details of when we need help.
The County Council have provided us with additional equipment including wheelbarrows, shovels, ropes, brush cutters and hedge cutters.
The FG have been invited to speak at the forthcoming Cambridgeshire Flood Conference.
Alconbury Brook Flood Group Report July 24th 2022
Alconbury Brook Flood Alleviation Scheme
40 Ponds project (Landscape Recovery/NFM)
CIL funding
Applications need to be in by end of August. Full discussions with PCs yet to be held
Volunteer projects
The FG are starting to construct a schedule of volunteer work fore the autumn/winter which will include clearance near the Dutch arches in AW and tree clearance around the Black Lodge pond. Previous targeted areas will be re-visited.
Alconbury Fete
A good number of visitors to our stall including many younger ones who wanted to save the doggies at Holly Lodge and the babies in the Alconbury’s by slowing the flow in the guttering models. Older ones who shared recollections of previous floods
The Alconbury Brook Flood Group Report May 2022
The Flood Group has had a number of meetings with the Environment Agency (EA) and Jacobs to prepare for the public consultation meeting on June 14th. The purpose of this public meeting is to get broad views on a range of options including ‘do nothing’ and ‘do minimum (status quo).
We have commented in detail on a number of proposals. The criteria we applied are in the box below
At the time of writing, we do not know which options will be presented but hope that our own preferred option will be included.
It is likely that other options from the unsuccessful 2005 and 2007 appraisal processes will be included to give the community a choice.
We have also walked from 1km downstream of the flyover to Holly Lodge with members of the EA Options Team pointing out opportunities and major obstacles within each option for example, damage to upstream or downstream businesses.
The public meeting will take place on June 14th at the Sports and Social Club between 2.00 and 7.30p.m. Please encourage people to attend.
The FG is about to send out a newsletter, and will also send out a public meeting reminder a few days before the 14th.
The FG held a successful AGM with about 40 people attending and nearly an hour of questions.
The Flood Group Charity also held its AGM.
The boat has finally been launched. Several members had a go during an enjoyable afternoon. We persuaded Mr Djonogly to have first go (in case of leaks). All survived the event and the boat will be in action soon.
A further phone meeting with the clerk of the course at Huntingdon Racecourse looked at issues of mutual interest.
More dead trees near Polecat Lane have been removed by volunteers.
Alconbury Brook Flood Group report for April 2022
There has been further progress with shortlisting options for the Alconbury Flood Alleviation Scheme. (The number of options has been reduced first from the original 31 to 11 then to 3). A consultation involving Flood Group members and Parish Council members is under way on the three options currently scoring best. We have been invited to provide feedback on May 6th. This is still an early stage. Full community consultation will follow when the best option/s are converted to into detailed plans. This will occur in the summer. Jacobs and the EA, with our help, will then build a business case to get funding from the Flood Prevention Capital Programme.
The EA (KP) have held an initial meeting with landowners from Alconbury to Steeple Gidding with a view to making a bid for an DEFRA pilot scheme (Landscape Recovery) which could improve freshwater habitat and flood mitigation. The Flood Group will be providing admin support for the bid.
Subsequently a smaller group have held a more formal Landscape Recovery meeting. Flood Group members will be contacting all landowners to construct a scheme. Likely ideas could include a network of new and refurbished ponds providing enhanced habitats and flood water storage; floodplain refurbishment enhancing habitats adjacent to water courses and their capacity; and well-designed leaky dams.
Volunteers have removed 7 more dead trees from near Polecat Lane as part of a long-term project to replace the trees with a hedge.
The Flood Group Charity has had its inaugural meeting. On 10th May 2022, the Charity will hold its AGM at the Sports and Social Club. Straight after the Charity’s AGM, the Flood Group will hold its AGM, which will be open to the public.
Alconbury Brook Flood Group report for March 2022
Volunteers have removed 3 trees from the brook near Polecat Lane. They have also cleared vegetation from the back of 2 gardens on the High Street Alconbury.
We have with the landowners permission started to remove other dead trees near Polecat Lane. We have consulted the EA about this work and plan to plant hedging to replace the gaps left by the trees in the autumn.
We have 4 permit exemptions for clearing silt adjacent to culverts and grips in Alconbury Weston and Alconbury. This work will take place over the next few months. On the basis of legal advice through the County Council we have made arrangements for expert ecological advice prior to any work to ensure nesting birds and spawning fish are not disturbed.
Our yellow boat is licenced to go anywhere on the Ouse and its tributaries. We are looking forward to launching it soon.
We have met with Jacobs who have completed the first phase of their work. We discussed the long list of 31 schemes which has been reduced to about 10. All members of the committee were consulted including Parish Councillor members. There was a fair degree of convergence in our views and those of the EA and Jacobs. Our favoured schemes remain in the running. We also discussed weighted criteria for additional shortlisting which includes cost, flood mitigation effectiveness, social impact and wellbeing, environmental cost/benefit.
We have continued to work with landowners on NFM schemes. Our current plans will cost approx. £75,000. The Flood Group Charity trustees are looking at charitable funding for this work.
We have agreed to support the EA in a Defra pilot scheme called Landscape Recovery. This involves the re-wilding of water courses, for example the construction of new ponds, re-connecting flood plains and leaky dams. The first meeting of this project with the EA, flood group members and 20 landowners from the catchment takes place on 28th March. The Flood Group have agreed to support and administer this project. Information from Defra remains a bit sketchy, so we are still a bit cautious about wholehearted support and have our own questions.
We met with the Clerk of the Course at Brampton Racecourse. Like us they suffered considerable damage because of the 2020 flood. We discussed areas of common interest including slowing the flow of flood water upstream of the villages.
The Flood Group AGM open to the public will take place on May 10th at 19.00.
Alconbury Brook Flood Group report for February 2022
A little more volunteer work has been done near the ford in Alconbury Weston. Volunteer work will be limited from mid-March because fish spawning and water birds nesting.
The brook is running too fast at the moment, but we hope to have one more volunteer event before early March. We now have permits to remove silt from where road drains are depositing sand and silt into the brook. Also work on the gardens of High Street properties in Alconbury and Alconbury Weston.
We have a small yellow boat for work in the brook when safe!
Generally we are very positive about the work done by the EA since Christmas particularly in Alconbury Weston and downstream of the A1 flyover. Some debris still to collect. The flood group has volunteered to do this but we await a reply. Between Polecat Lane and Alconbury Weston there is still some work to do, but volunteers could do this.
The Flood Group committee have met and agreed to hold an AGM in May, which will be open to volunteers and the community generally.
On behalf of the Alconbury communities and having consulted the PCs, the Flood Group have signed off the new improved brook CCTV agreement with the EA.
Progress is being made with the Flood Alleviation modelling. On request from the EA the Flood Group have consulted the PCs with regard to (statutory) access arrangements for a future public consultation. The main issue will be ensuring everyone, including those without internet access, is aware and people in the communities with special needs will be able to participate if they wish.
A disappointment has been that LENs, who had been very positive about funding all of our upstream NFM, have withdrawn their offer. They had wrongly assumed that some of the land was in Northamptonshire. As Cambridgeshire does not subscribe to LENS, we do not qualify for financial assistance from LENS. Much effort has been spent this month looking at alternatives to overcome this problem. We are seeking alternative sources of funding. Charles Krolik-Root has organised a meeting in early March with Think Communities to assist with this.
Before seeking funding elsewhere, we have had to ask landowners to ask the RPA to calculate any losses that may occur as a result of us installing NFM. This is likely to be quite small, but we are committed to ensuring farmers will not lose out. We now have potential projects on 4 farms and we hope to have feedback through the landowners from the RPA shortly.
Through countryside stewardship we have acquired free ADAS hydrology/NFM consultancy which will enable us to understand the optimum positions (on watercourses) for the projects we have agreed. We were pleased that 3 landowners have authorised us to have this work done. Reporting will occur in May/June which is in good time for construction in the summer/autumn. In the meantime, further design work has been done.
We remain vigilant. Some very high rainfalls have occurred previously in March and April. Our measurements suggest the soil is now full. We are measuring flow at Alconbury. There appears to be a small flow improvement, but our comparison may not be like for like.
Alconbury Brook Flood Group report for 20th January 2022
Since mid- December, (our brilliant) flood group volunteers have
The EA completed most but not all of the bank maintenance in November. Those sections missed were discussed during a very helpful site visit with the EA Assets Manager During the week starting 17/1 EA teams have undertaken a significant amount of additional bank clearance and will continue over the next 2 weeks providing the weather holds.
We have arranged to do some clearance ourselves which complements that done by the EA teams including the banks of riverside properties in the High Streets of both Alconbury and Alconbury Weston. This is scheduled for the second week in February. To facilitate this the flood group have ordered a boat.
We now have third party insurance, and our volunteers are insured against personal accident.
Another farmer has agreed to have an off-line storage pond, together with some leaky dams on an Alconbury Brook tributary watercourse. The idb have give outline agreement to the work which is on a watercourse under their jurisdiction. We hope that funding and consents will become available so that work can be done in May/June.
Further upstream two flood group members had a preliminary meeting with another farmer who has given us permission to look around his farm for suitable places for some small holding structures on 26/1. We will be discussing funding with LENs.
We have had an update from the EA with detailed plans for an NFM system on the East side of Vinegar Hill. The is a slight delay while this is modelled but the project could be installed in late spring/summer 2022.
The EA modelling contract with Jacobs has finally been signed off and work has begun. At some point the consultant will visit the Alconbury’s to understand the lie of the land, and the opportunities which exist given the strong commitment from the communities involved.
Flood Group Newsletter 2, part funded by Alconbury Parish Council will be distributed between 17/1 and 26/1
An improved flood CCTV system will be operational soon. There remain some unanswered questions about fields of vision and distribution of passwords, but these should be resolved shortly.
It has been very dry, only 29mm of rain in the first three weeks of January, however we are certain that water in the brook is running away faster because of the better maintenance. Soil moisture varies but has been as low as 80% (our monitoring) in the last 2 weeks providing a small buffer for heavy rain. Long may it continue!! We now have portable flow monitoring equipment. On 18/1, the flow was about 0.1cubic meter/sec at the A ford and 0.095 cubic meters per second AW ford (in December 2020 the flow at Alconbury flyover was 94 cubic meters / second). The EA have invited the Flood Group to suggest two sites for permanent flow monitoring equipment.
Alconbury Brook Flood Group report for December 2021
During December, volunteers have cleared further sections of bank not done by EA contractors (see left) and discovered long forgotten benching (low shelf cut into bank). They have also done further clearance upstream of the heritage bridge to the old ford.
The EA have not yet returned to do work they had promised to do by Christmas but have re-visited the site to draw up a detailed specification and have now said that it will be done in January. This is all of the sections not done by the contractors including downstream to Labcorp (Covance) on the north bank, Brooklands Farm, improvements downstream of Alconbury Weston and near the ford in Alconbury Weston.
The FG have been told that their bid for funds from CCC has been successful. This will allow the purchase of safety equipment, additional tools, a small flat-bottomed boat and other items.
The EA have commissioned another off-line storage pond this time at Winnick. (not sure of the details but I believe it stores water from a significant ditch just north of Hamerton before it flows into Alconbury Brook.
Rusts Lane pumps have now been repaired.
The FG have now opened a bank account.
The FG has been working with the Land Enterprise Network (LENs) who channel money from large companies into environmental projects. We have made site visits to them to sites where landowners have agreed in principle for significant NFM including 2 off-line storage areas = 25,000 cubic meters, a refurbished pond and 5 leaky dams. Optimistic that LENs will pay for this work to be done @£50,000 starting April 2022
Community is finding info@alconburybrookfloodgroup.uk resulting in enquiries and offers of help.
In the last 3 months we have had 7 enquiries from people wishing to move to the villages and wanting information.
EA consultants (Jacobs) have now started work on modelling and evaluation of a major flood mitigation scheme after delays from heritage section of EA and then further negotiation with Jacobs about timescales. Still on track for public consultation summer 2022. Currently long list includes elements of previous plans plus FG reservoir proposals (Slow stretch and Store) and proposal for a 2-stage channel. Photograph above is an example of a 2-stage channel
FG has started to do soil sampling since soil capacity is as important a factor as rainfall in predicting flooding. Soil is now fairly full but earlier this month it could have absorbed most of the rain that caused flooding in December 2020.
Second newsletter will be distributed before the next Parish Council Meeting
January 8th is our next volunteer day, also volunteers are tree planting on (probably) January 15th. Equipment purchased with the CCC grant will allow us to do work in Alconbury Weston on January 8th.
Alconbury Brook Flood Group report for November 2021
Volunteers have now cleared 600m of brook bank and bed including most recently:
The Environment Agency have carried out their annual maintenance of banks and reed spraying. In many places this has been done reasonably well but a number of stretches are less well done or have been missed altogether. We walked the brook from 800m downstream of Alconbury to Alconbury Weston with Chris Collin the EA manager. Chris Collin has committed to doing much of the outstanding bank clearance by Christmas, while Flood Group volunteers will do several other smaller sections.
An application for a grant has been made to the County Council for the Flood Group to clear banks adjacent to 2 and 6 High Street Alconbury and a brook bank common land strip adjacent to 2,4,6,8,10,12 and14 High Street Alconbury Weston.
The County Council have let us know that work will start on the Rusts Lane pumps on November 25th.
Volunteers dug out 4 grips on the School Lane ditch.
The Flood Group have adopted a 7 year plan which will be shared with Parish Councils as soon as possible for them to also adopt.
The Flood Group have worked with several farmers upstream of Alconbury Weston. A plan including a number of leaky dams and off-line storage has been submitted to the internal drainage board for comment. Once all consents have been acquired the Flood Group hope to start work in January.
The Flood Group has a web-site (still being developed) and an email address: info@alconburybrookfloodgroup.uk.
The group will be circulating their first newsletter before the end of November to all residents in Alconbury, Alconbury Weston and Hamerton.
The Flood group team are keen to take action to reduce flow upstream and will be testing out the concept of Temporary Test Dams TTD.
The video shows a fallen treee that could be anchored to either site of the brook and act as a natural dam to encourage biodiversity as well as act as a dam during a flood event
We need your consent to load the translations
We use a third-party service to translate the website content that may collect data about your activity. Please review the details in the privacy policy and accept the service to view the translations.